The City's Utility Infrastructure includes potable water, reuse water, stormwater, sewer. Our water treatment plan provides 7.1 million gallons of treated drinking water daily. The City's utility infrastructure system includes 81 miles of water transmission and distribution lines, 72 miles of gravity sewer and force mains, 42 miles of stormwater, and 16 lift stations.
The City of Hallandale Beach has an aged and stressed utility infrastructure. Over the years multiple studies have assessed and recommended immediate rehabilitative measures be initiated to mitigate against catastrophic infrastructure failures. Additionally, increased development within the city has necessitated capacity improvements be made to meet the incoming service demands.
The 2022 Infrastructure Construction Plan was presented to the City Commission on April 6, 2022. It was prepared to be an outline of the construction schedule for the city's infrastructure rehabilitation. These projects are prioritized based on the recommendations assessed as urgent with in the 2016 Basis of Design Report, 2016 Wastewater Masterplan, 2019 Year Water Supply Plan and the 2014 Water, Wastewater and Stormwater Facilities Plan. These projects have been reviewed and prioritized on the recommendations of the Engineering Team of the Public Works Department based on need.
This process will be challenging and test the fortitude of our city. The result of this effort will establish a secure, and stable utility for decades to come.
View the full presentation here: Infrastructure Construction Plan
View the News Release here: 2022-0830 NEWS RELEASE HB Infrastructure
Completed Projects
Foster Road Water Main Replacement
-
Foster Road WM Before_003
-
Foster Road WM After_001
-
Foster Road WM After_002
-
Foster Road WM After_003
-
Foster Road WM Before_001
-
Foster Road WM Before_002
Lift Station 8 Replacement
-
Lift Station 8 Replacement Before (1)
-
Lift Station 8 Replacement After (1)
-
Lift Station 8 Replacement After (2)
-
Lift Station 8 Replacement After (3)
-
Lift Station 8 Replacement Before (2)
-
Lift Station 8 Replacement Before (3)
High Service Pump Replacement
-
High Service Pump Before (3)
-
High Service Pump Before (1)
-
High Service Pump Before (2)
-
High Service Pumps After (2)
-
High Service Pumps After (3)
-
High Service Pumps After (1)
Current Projects
Atlantic Shores Roadway Improvement
- Atlantic Shores Public Meeting Presentation 01/30/20
- Atlantic Shores Blvd COAT Meeting 2 03/04/20
- Project Progress 10/31/20
Atlantic Shores Watermain Replacement (NE 14th Ave)
- Project in Design
Community Development Block Grant 49
- Project in Design
Community Development Block Grant 48
- Design Completed
Community Development Block Grant 47
FDOT Beautification
- Project Progress Notification 10/31/20
Force Main Replacement (30")
- Project in Design
Force Main Replacement NE 7th Avenue
- Project in Design
Lift Station 1 Replacement Project
- Project Design Pending
Lift Station 2 Rehabilitation
- Project Design Complete, bid in process
Lift Station 3 Rehabilitation
- Project in Design
Lift Station 4 Rehabilitation
- Project in Design
Lift Station 5 Rehabilitation
- Project in Design
Lift Station 6 Rehabilitation
- Project in Design
Lift Station 9 Rehabilitation
- Project in Design
Lift Station 10 Rehabilitation
- Project in Design
Lift Station 11 Rehabilitation
- Project in Design
Lift Station 12 Rehabilitation
- Project in Design
Lift Station 13 Rehabilitation
- Project in Design
Lift Station 14 Rehabilitation
- Project under construction
Lift Station 15 Rehabilitation
- Project in Design
Lift Station 16 Rehabilitation
- Project in Design
North Miami Beach Booster Rehabilitation
- Project in Design
Schaffer Canal Rehabilitation
- Project Design Complete, bid in process
Three Islands Reuse Irrigation Project
- Project Start Notification 01/11/17
Transfer Pump Replacement
- Project Start Notification 04/08/21
Water Main Design NE 7th & NE 18th Avenue
- Project in Design
Water Main Replacement Layne Blvd
- Project in Design
Water Main Replacement Three Islands
- Design Pending